New Sewers for Liege Airport

Liege airport required a new sewer system, so a scheme was developed to install some 6.3 km of new sewers beneath the airport. The main contractor for the work was Denys.


Click here to jump to the testimonial statement.


 

The programme of work included the installation of some 933 m of ID1800mm diameter pipe using microtunnelling techniques. Denys engaged experienced microtunnelling contractor K-Boringen to complete this part of the project.

The microtunnelling works were to be completed using the contractor’s Herrenknecht manufactured microtunnelling machine which utilised a TUnIS Navigation MTGyro guidance system from VMT. What made this operation unusual is that, where normally an HWL (Hydrostatic Water Level) system would be used in conjunction with the Gyro system to establish elevation of the boring machine, on this project it was decided that this would not be utilised. This is believed to be the first time such a a pipe jacking project has been undertaken by the contractor without the HWL. This was decided to simplify operations during excavation.

In order to maintain the required tolerances and in particular not to create a counter slope, control measurements were planned at intervals of approximately 60 m. This corresponds to a typical control measurement interval when using gyro navigation systems.

The control measurements were carried out by the specialists from VMT, who were on site during the entire course of the project in order to optimally support the new generation system TUnIS Navigation MT. Since the intention was to extend the control measurement intervals above the usual 60 m, a tunnel laser was installed parallel to the gyro system, which was used to spot-check the determined position.

The navigation with gyro compass and without hydro level has proven itself in this project, with the specified tolerances being adhered to at all times.

Given the location of the new sewer under the high speed double-track railway Liege – Namur, the project also utilised a VMT MODUS (Modular System for automated Deformation Monitoring) system to monitor the deformation of the rails, an application which is rather unusual for microtunnelling projects where bore diameters are relatively small and ground deformation is usually extremely limited.

Commenting on the Liège project for K-Boringen, chief operating officer Wim Feyen said:

“Working without the use of the hydrostatic water level simplified the handling of the drive considerably. Due to production requirements the intervals of our check surveys to monitor the accuracy of the gyro guidance system were a little longer than we would have liked. However, despite this, the alternative calculation method for the vertical position has reached the accuracies that VMT had stated in advance and the bore has been completed within the required tolerances.

For tunnels with very small gradients, it wouldn’t be optimal to rely solely on this new calculation method – however, this project has shown us that, with the right equipment and the right back-up, we can achieve the necessary accuracy of the drive without a hydrostatic water level.”

 

At a Glance Fact Sheet:

Project Name or Designation/Timescale Seraing, Sowaer – two months
Location Liege, Belgium
Project requirement
New sewer system
Method Microtunnelling/Pipe Jacking
Diameter/Length/Bend Radius Diameter 1,800 mm, length 933 m, straight
VMT System utilised TUnIS Navigation MTGyro

Plus MODUS as additional monitoring system (a rare case for a microtunnelling project)

Challenges The TUnIS Navigation MTGyro navigation was used without an HWL (Hydrostatic Water Level) system and so required additional control and extremely high accuracy of check surveys