DE CN

News

+ + +

September 2021

New Sewer Project Protects Emscher River

The sewerage system in and around Herne is undergoing a transformation as part of a project to protect both the Hüller Bach and Emscher River from wastewater discharges.

The Hüller Bach, a stream which flows through Herne in North Rhine-Westphalia, Germany, is the largest tributary of the Emscher River in the Ruhr area. For years the stream has effectively functioned as an above-ground sewer, with underground canalisation not possible due to the region’s coal mining activities.

As part of a project to protect both the Hüller Bach and Emscher River from wastewater discharges, under the designation of the Emscher conversion project, the sewerage system in and around Herne is undergoing a transformation. A cease in underground coal mining has brought with it the opportunity to move sewerage below the earth’s surface, with the construction of a new 2.6 km sewer pipe string running underground and parallel to the stream.

Since 1992, the Emschergenossenschaft has been planning and implementing the Emscher Reconstruction project in close coordination with the surrounding municipalities, in which almost €5.5 billion will be invested over a period of about 30 years. Sonntag Baugesellschaft mbH & Co. KG, the contractor appointed to undertake the recent microtunnelling works, elected to work with VMT as long-time partner and guidance specialist. A Herrenknecht AVN1600 machine, enlarged to OD2160, was utilised for the project, supported by VMT’s navigation systems SLS-Microtunnelling LT and TUnIS Navigation MTLaserTotalstation.

Excellent collaboration between VMT and Centerline – who undertook the surveying for the project – contributed to the quick and successful completion of the excavation.

 

Three Successful Curved Drives

The new sewer sections were to be installed in three drives. Drive 1, covering a length of 350 m with a minimum curve radius 480 m, was completed in December 2020. Drive 2, completed between February and April 2021, had a length of 900 m with a minimum curve radius of 450 m. Drive 3 had a length of 700 m with a minimum curve radius of 450 m. This final drive was completed between April and May 2021.

Drive 1 utilised the standard SLS-Microtunnelling LT navigation system. This system is designed with a laser target unit, with a tunnel laser mounted in the start shaft of the drive and an active target unit placed in the machine. Data from the laser target continuously determines the exact position of the machine and displays any deviations from the desired alignment immediately on the monitor at the operator’s position. According to Sonntag Baugesellschaft, Drive 1 was described as ‘a winding 350 m long drive’ which ‘broke through the target seal with pinpoint accuracy’.

For the two longer drives with tighter curves, the contractor utilised TUnIS Navigation MTLaserTotalstation, VMT’s latest incarnation of its laser-based guidance systems. In addition to the long distance and tight curvature of the latter drives, further challenges arose as a result of drilling restrictions on site. Usually, installation of the VMT system hardware takes place with the drilling and tightening of screws, allowing an easy workflow and flexibility in case of line-of-sight problems. For this project, however, drilling was not allowed in the tunnel as the inner surface of the pipe string needed to remain unaltered: as a result, sight distances needed to be precisely calculated in advance. In order to securely mount VMT hardware without the use of standard screws, tension rings were used during installation.

TUnIS Navigation MTLaserTotalstation allows precise and efficient navigation of curved and long-distance drives. The expert system is based on the principle of invariance, where the horizontal and vertical position of the machine is determined by a laser total station in conjunction with several reference and target prisms and an electronic target unit inside the machine. The laser total station is permanently installed in the pipe string. An inclination sensor integrated in the electronic target unit measures pitch and roll of the machine. The system is drift and refraction-independent and requires 50% less control measurements than the gyro-based all-rounder system. This equates to less interruption of tunnelling, shorter downtimes, and significantly increased tunnelling performance.

With the main pipe string successfully completed, the project will end later in 2021 with the connection of the lateral sewer connections. This includes the connections at the Herne-Königsgrube pumping station, Herne-Hordeler Heide and the connection of the Herne-Röhlinghausen pumping station to the new sewer of the Emschergenossenschaft.

 

At a Glance Fact Sheet:

Project Name or Designation/Timescale TP 2020 3691 Herne Hüller Bach
Location Herne, Germany
Project requirement
Sewer Installation
Method Microtunnelling/Pipe Jacking
Diameter/Length/Bend Radius Diameter: ID 1,800 mm

Lengths:

  • Drive 1 – length 350m, min. radius 480m in 2020 (Dec.)
  • Drive 2 –  length 900m, min. radius 450m in 2021 (Feb. – Apr.)
  • Drive 3 –  length 700m, min. radius 450m in 2021 (Apr. – May)
VMT System utilised SLS-Microtunnelling LT (used in Drive 1)

TUnIS Navigation MTLaserTotalstation (used for Drives 2 and 3)

Challenges Sight distances would have to be calculated precisely because it was not possible to drill in the tunnel. In order to securely mount VMT hardware without the use of standard screws, tension rings were used during installation.